Lien waiver: the four types and when to sign each

By The AR Agent team · · 7 min read

A lien waiver is a document in which a contractor, subcontractor or supplier gives up some or all of its right to file a mechanics lien on a property, usually in exchange for a payment. The safe rule: sign conditional waivers before you are paid, and unconditional waivers only once the money has cleared.

This page is general information about US practice, not legal advice. Lien law is set by each state.

What is a lien waiver?

A mechanics lien is a claim against a property by someone who improved it and was not paid. A lien waiver (or "waiver and release") is the document that gives that right up. Owners, lenders and general contractors collect them so they can show that everyone who worked on the job has been paid up to a point. Without them, an owner could pay the general contractor in full and still face a lien from an unpaid subcontractor.

What are the four types of lien waiver?

A conditional waiver only takes effect when you receive the payment it describes. An unconditional waiver is effective once signed and delivered. A progress waiver covers work through a stated date. A final waiver covers the whole job.

Type What it releases When to sign
Conditional, progress Lien rights through a stated date, once the stated payment is received With your pay application, before payment
Unconditional, progress Lien rights through a stated date, effective immediately After the progress payment has cleared
Conditional, final All lien rights for the job, once the final payment is received With your final invoice or retainage request
Unconditional, final All lien rights for the job, effective immediately After the final payment has cleared

California's Civil Code sets out one form for each of these, in sections 8132 (conditional, progress), 8134 (unconditional, progress), 8136 (conditional, final) and 8138 (unconditional, final). Texas Property Code 53.284 sets out the same four.

When should you sign each type?

Say a subcontractor bills $40,000 and the general contractor wants a waiver before paying.

  1. Send a conditional progress waiver with the pay application, for $40,000 through the end of the billing period.
  2. When the payment arrives and has cleared your bank, send an unconditional progress waiver if one is requested.
  3. At the end of the job, send a conditional final waiver with the final invoice or the request for retainage release.
  4. Once the final payment has cleared, send the unconditional final waiver.

Check the "through date" and amount on every waiver. List any exceptions, such as retainage still held or unpaid extras. California's conditional progress form has space for these.

Why is signing an unconditional waiver before payment risky?

It works whether you were paid or not. California's unconditional progress form carries a notice to the claimant that the document is enforceable against you if you sign it, "even if you have not been paid." The Texas unconditional forms carry a similar notice, and tell anyone who has not been paid to use a conditional form instead.

If you sign one and the payment never clears, you may have given up your lien rights for that amount and be left with an ordinary unpaid invoice.

Conditional waivers protect both sides: the payer gets a waiver that switches on when it pays, and you keep your rights until then. Under California Civil Code 8124 and Texas Property Code 53.281, a conditional waiver only releases lien rights if there is evidence of payment to the claimant.

Do some states require a specific lien waiver form?

Some states set out the exact wording. A few examples:

  • California. Civil Code 8124 says a waiver releases lien and bond rights only if it is in substantially the statutory form and signed by the claimant. The forms are in sections 8132 to 8138.
  • Texas. Property Code 53.281 says a waiver must substantially comply with one of the forms in section 53.284 to release the owner, the property, the contractor and the surety.
  • Florida. Statutes 713.20 sets out a "Waiver and Release of Lien upon Progress Payment" and a "Waiver and Release of Lien upon Final Payment", and says a person may not require a lienor to furnish a waiver that is different from those forms.

If a general contractor sends its own form, compare it with the statute and the payment you are receiving before signing.

How do lien waivers tie into getting paid?

The waiver is often a condition of payment, which makes it a common blocker:

  • The waiver was not sent with the pay application.
  • It was sent on the wrong form, or for the wrong amount or date.
  • A lower-tier supplier's waiver is missing, so the general contractor is holding the whole payment.
  • The payer wants an unconditional waiver before paying.

When a payment is late, ask directly whether anything is missing, and fix it the same day:

Subject: Pay application [Number] - [Project name] - waiver attached

Hi [First name],

Pay application [Number] for [Amount], covering work through
[Through date], was due for payment on [Due date].

I have attached our conditional waiver and release on progress
payment for that amount and period. We will send the unconditional
waiver as soon as the payment has cleared.

Is anything else holding this up? If so, we will send it today.

Thanks,
[Your name]
[Company name]

For the stages after that, our past due invoice email templates and the guide to how to collect unpaid invoices set out the escalation steps.

Frequently asked questions

What is the difference between a lien waiver and a lien release?

The terms overlap and are often used interchangeably. California and Texas both use "waiver and release" in the names of their statutory forms.

Can I be asked to waive lien rights before I start work?

In some states, an advance waiver is not enforceable. Florida Statutes 713.20, for example, says a right to claim a lien may not be waived in advance. Rules differ by state, so check before signing anything that waives rights for work not yet done.

What should a conditional waiver say?

California's form names the claimant, customer, job location, owner, the through date, the payment amount and any exceptions, such as retentions or unpaid extras. If your state has a statutory form, use it.

What if I signed an unconditional waiver and was not paid?

Speak to a construction attorney in the project's state quickly. You may have released your lien rights for that amount, but the invoice can still be owed under your contract. Keep chasing it in writing.

Can a general contractor make me use its own waiver form?

It depends on the state. Florida Statutes 713.20 says a person may not require a lienor to furnish a waiver that is different from the statutory forms. In California and Texas, a waiver only works as a release if it substantially follows the statutory form.

How The AR Agent handles this

The AR Agent follows up overdue invoices by email, using the due dates in QuickBooks or Xero. It reads what customers write back. If a general contractor replies that a payment is waiting on a lien waiver, the wrong form, or a missing document, it identifies that blocker and brings it to your team instead of sending another reminder. When a reply says "it will go out once we have the waiver", that can become a tracked payment promise with a follow-up if the date passes. If a reply needs judgement, it asks a person. Every email, promise and blocker is kept on the customer's record.

Talk to us: our AI agent chases your invoices until you are paid.

Sources

Let us chase your overdue invoices

Connect QuickBooks or Xero and your finance inbox. We’ll help you set it up. No card or contract.

Accounting software

No card required.